David Roberts
By now, you’ve probably heard that tons of new renewable energy projects are “stuck in the interconnection queues,” unable to connect to the grid and produce electricity until grid operators get around to approving them, which can take up to five years in some areas.
And you might have heard that FERC recently implemented some reforms of the interconnection queue process in hopes of speeding it up.
It all seems like a pretty big deal. But as I think about it, it occurs to me that I don’t really know what an interconnection queue is or why they work the way they do. So I’m going to talk to an expert — Chaz Teplin, who works on carbon-free grids with RMI — to get the lowdown.
We’re going to talk through the basics of interconnection queues, why they’re so slow, what RTOs and FERC are doing to reform them, and what remains to be done (namely some friggin’ regional transmission planning).
With no further ado, Chaz Teplin. Welcome to Volts. Thank you so much for coming.
Chaz Teplin
Thanks for having me.
David Roberts
You know, as I said in my intro, it seems like the clean energy community at this point has heard the term interconnection queue enough times that they all know it enough to say it, right. We know on some level that interconnection queues are slowing things down and they're backed up and that's why we're not building renewable energy as fast as we should be. But I suspect that quite a few of my listeners are roughly where I am, which is that's basically where my knowledge runs dry. I can say the words, so I'm excited to talk to you about what the heck they are, why they exist, etc., how to solve them, etc.
So maybe let's just start with why is it that all of a sudden everybody's talking about interconnection queues? Why has this come to the top of the pile recently?
Chaz Teplin
Yeah, everybody's talking about interconnection queues and there's been a recent order from FERC amid the hullabaloo. Right. So I think it's a good news, bad news story. The good news is that there's currently two terawatts of generators asking to connect to the US grid. And almost all of that two terawatts is clean energy, wind, solar and storage. So for those of us that have been in the business for a while, this is unbelievably great news. That means there's so many projects out there of clean energy mostly there's some gas, but clean energy mostly that believe it's economic to connect to the grid and they're willing to pay a fee in order to ask to connect.
David Roberts
And how much is that relative to what's currently on the grid?
Chaz Teplin
Yeah, it's not exactly an apples to apples comparison, but two terawatts asking to connect 1.25 terawatts approximately on the US grid today.
David Roberts
Right. So there's more waiting to get on than exists currently on the grid. Now, we know, I'm sure you're going to say, we're going to say probably 50 times during this pod, just because something's in the queue doesn't mean it will necessarily get built. So it's not like all of that two terawatts is real or inevitable, but still, the fact that more is waiting to get on the grid than currently exists on the grid is quite striking.
Chaz Teplin
That's right. And every year more is asking to connect, right? So, yeah, absolutely, it's not going to all get built. But I think it's a fairly clear demand signal that generators and developers are giving. They want to connect to the grid. They believe they ca