FERC is about to make some very important decisions about transmission
The Federal Energy Regulatory Commission (FERC) is poised to pass new policy that will expand regional transmission capacity, but how impactful will its new rule be? In this episode, grid policy expert Rob Gramlich gives the lay of the land.
(PDF transcript)
(Active transcript)
Text transcript:
David Roberts
By now, it’s fairly well understood that the US badly needs more electricity transmission lines to keep up with the changing generation mix and growth in demand that will come with clean electrification. But new lines, especially the much-needed longer-distance regional lines, are being built at a snail’s pace. If the US is to hit its mid-century climate goals, transmission capacity expansion must radically accelerate.
Congress helped a little with money in the infrastructure bill, and the Biden administration helped by establishing a Grid Deployment Office inside the Department of Energy, but arguably the biggest opportunity for progress comes in the form of an upcoming rule by the Federal Energy Regulatory Commission (FERC).
It will beef up the commission’s existing rules on regional transmission planning, but exactly how much it will strengthen them depends on the final rule, expected early next year. Transmission advocates are urging FERC to pass a rule with reel teeth — including Senate Majority Leader Chuck Schumer, who sent the commission a letter with encouragement and suggestions in July.
Nobody knows more about grid policy than Rob Gramlich, founder and president of Grid Strategies, a policy analysis and strategy firm. He is executive director of the WATT Coalition, co-founded and used to run Americans for a Clean Energy Grid, serves as a board advisor to a half-dozen other groups, and has a long history in the industry, including a stint at FERC in the early 2000s.
I talked with Rob about the current state of affairs in transmission policy, the scope of FERC’s authority, and the details that matter in the coming rule. Don’t let the technical-sounding subject scare you off — this was a fun one, and incredibly clarifying.
Okay then, with no further ado, Rob Gramlich. Welcome to Volts. Thank you so much for coming.
Rob Gramlich
Thanks, David. Great to be here.
David Roberts
I am excited to talk about this. I know that perhaps FERC is not at the top of people's mind when they think about excitement and thrills, but I think people will see by the end of this why this is a very good time to tune in to what FERC's doing. So let's start here. I think we can assume for the purposes of this pod that Volts listeners understand the need for more transmission, specifically the need for more long-distance transmission for a bunch of reasons. We know that the resource mix is changing. We care more about renewables now.
They're located in different places. They're located not necessarily next to load. They're remote. We're going to double or triple the amount of electricity we're using in the coming years, because we're electrifying everything. So we need more transmission for that reason. We know that connecting up a wider geographical area makes the whole system more reliable, makes the whole system cheaper. Transmission is the wonder tool of energy. It makes everything better, and yet we are not building it. So back in the late 90s, FERC, the Federal Energy Regulatory Commission, which has jurisdiction over interstate transmission, released a series of orders.
So in the beginning, there were, just across the nation, just dozens and dozens of individual vertically integrated utilities, all of which were buildi